In 2012, Insinööritoimisto Seppo Rantala Oy used a steel
shoring system to support the nearly 200-metre-long
moulds for the highway bridges in Tikkalansaari. “The critical
aspects of the schedule were held excellently. Thanks to the
support scaffolding provided by Telinekataja, we saved up
to two months per bridge, as we could efficiently utilise our
carpenter resources for mould building,” estimates CEO
SAMI
RANTALA
.
In Harjavalta, the shoring tower system was used to
support the 625-tonne concrete vault of the water intake
channel of the hydropower turbine. Telinekataja offered us
a solution that enabled us to support the concrete vault and
SHORING SYSTEMS FOR SUCCESSFULL CONSTRUCTION PROJECTS
– Telinekataja tarjosi meille ratkaisun, jota käyttämällä
voimme tukea betoniholvin ja suorittaa myös seinien muot-
ti- ja raudoitustyöt sekä betonityöt samalta telineeltä, kertoi
Skanska Talonrakennus Oy:n projekti-insinööri
PETRI PU-
PUTTI
.
Spiraalin yläosan massiivivalu suojattiin sääsuojalla,
jotta betonityöt saatiin tehtyä myös talvisissa olosuhteis-
sa. Uusi vesiturbiini otettiin käyttöön syksyllä 2016, jonka
jälkeen korjataan kaksi vesiturbiinia. Rakennushankkeen
kustannusarvio on 40 miljoonaa euroa.
use the same scaffolding to carry out work related to mould
building, reinforcing and casting,” explains Project Engineer
PETRI PUPUTTI
, Skanska Talonrakennus Oy.
A 185-metre-long bridge was completed in Pasila in
autumn 2015. During its construction, Telinekataja supplied a
6.5–11 m high shoring system to support the inclined mould
of the bridge. “We selected steel scaffolding primarily because
of the high support height required for the bridge mould, and
we also wanted to find an optimal solution in terms of on-site
occupational safety,” says
MIKKO SARESMA
, Site foreman,
YIT Corporation.
In recent years, Telinekataja has implemented shoring systems at several sites across the country.
Telinekataja’s TG 60 shoring systems were used, for example, in the construction of the Tikkalansaari
highway bridges in Kuopio, the Pasila bridge in Helsinki, and the 625-tonne concreting project at
the hydropower plant in Harjavalta. These large-scale projects were successfully completed, and
the construction companies gained substantial benefits from using the shoring systems.
Kalteva silta keskelle Pasilaa
YIT Rakennus Oy käynnisti Keski-Pasilan laajan rakennus-
hankkeen 185 metriä pitkän Pasilan sillan urakoinnilla. Syk-
syllä 2015 valmistuneen sillan kaltevan siltamuotin alle ra-
kennettiin 6,5-11 metriä korkea järjestelmätukiteline avaimet
käteen -palveluna.
– Terästelineiden valintaan vaikutti ennen kaikkea silta-
muotin korkea tuentakorkeus ja työturvallisuuden kannalta
parhaan vaihtoehdon hakeminen. Terästelineet tulevat hyvin
todennäköisesti syrjäyttämään puutavaran siltamuottien tu-
kitelineinä, kertoi vastaava työnjohtaja
MIKKO SARESMA
YIT
Rakennus Oy:stä.
Telinekataja kytki tukitelineeseen myös liikkumista hel-
pottavan porrastornin, ja hyödynsi sillan liikenneaukkojen
kohdalla järeämpiä ART-tukitorneja, joilla päästään jopa 60
tonnin kantavuuksiin. – Puusta rakennettujen tukitelineiden
toteuttaminen olisi vienyt selvästi enemmän aikaa, sanoi YIT
Rakennus Oy:n työnjohtaja
JANI KILLI
.